ACROW Bridges Yasutake and Akulikuli #2 |
This Project plans to install 30-40 foot long pre-engineered Acrow Bridge systems with approach ramps on either side at both Kahuna Road, Kapaa Homesteads, Kauai, HI and Kamalu Road, Wailua Homesteads, Kauai, HI.
Project Manager:
Donald M. Fujimoto, P.E., M.B.A.
PH: (808) 241-4083
|
|
Phase:
Cost:
- Design: $300,000.00
- Construction: TBD
|
Improvements to Maluhia Road (Route 520) & Kōloa Road (Route 530) |
This Project will rehabilitate pavement on Kōloa Road, from Kaumuali‘i Highway to Po‘ipu Road, and Maluhia Road, from Kaumuali‘i Highway to Kōloa Road. This project also plans to extend the pavement shoulders by up to 6 feet in each direction, add a left turn auxiliary lane on Kōloa Road at Piko Road, add a left turn auxiliary lane on Kōloa Road at Lauoho Road, and add a left turn pocket on Maluhia Road to Ala Kinoiki. A roundabout will also be installed at the intersection of Kōloa Road and Ala Kalanikaumaka as well as guardrail repairs, drainage modifications, and other safety improvements.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map |
Phase:
Cost:
- Design: $1,102,500.00
- Construction: $1,500,000.00
|
Kawaihau-Hau‘a‘ala-Mailihuna Complete Streets Project |
The project aims to construct a peanut-shaped roundabout, sidewalks, paved shoulders, and various other roadway improvements to help improve the safety and operations of the 5-way intersection of these three roads and to people using multiple modes to travel efficiently and safely through Kawaihau Road, Hau'a'ala Road, and Mailihuna Road located in Kapaʻa, Kaua'i Island, Hawai'i. This area contains St. Catherine's School/Church, Kapaʻa High School, Kapaʻa Elementary School, Mahelona Hospital, and Gore Park.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map
Peanutabout Concept
|
Phase:
Cost:
- Design: $1,011,118.35
- Construction: $7,979,297.00
|
Kīpū Bridge Repair |
This Project will rehabilitate Kīpū Bridge to retain its original load capacity by preventing further loss of steel reinforcement and to install transitions between gaps of the bridge wall for safety.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map
Project Area
|
Phase:
Cost:
- Design: $208,854.00
- Construction: TBD
|
Kōloa Bridge Repair |
This Project will rehabilitate Kōloa Bridge by repairing the road surface, which will be repaved and restriped within the area of the bridge as well as immediately before and after the bridge. This rehabilitation also plans to fix spalls and delamination to prevent further loss of the exposed steel reinforcement, bring the bridge strength up to current standards by repairing and augmenting the beams, and add guardrails on the west and east sides of the bridge’s mauka-side wall.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Project Area |
Phase:
Cost:
- Design: $201,331.00
- Construction: TBD
|
Niumalu Bridge |
This Project will improve the safety for vehicles crossing the one-lane bridge at Pū‘ali Stream near Nāwiliwili Harbor as the current bridge is heavily spalled with a large amount of section loss in the exposed reinforcing steel. This improve will include rehabilitation of the existing, damaged concrete bridge deck that will match the original bridge in design, color, texture, and other visual qualities. New bridge ends will be constructed on dry land behind the existing ends and the new bridge deck will span over the existing ends. The existing ends will remain as-is.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map |
Phase:
Cost:
- Design: $374,291.00
- Construction: TBD
|
Olohena Road (RTE 581) Resurfacing |
This Project, located in the Kawaihau District, will include pavement restriping, roadway surfacing, shoulder widening, construction of sidewalks, striping of pedestrian crossings, improvements to accessible routes, reconfiguration and/or addition/deletion of travel lanes, turn lanes, bike lanes, and parking areas, replacement or upgrades to bus stops, vegetation removal, removal of trees that endanger life or property, storm drainage improvements, replacement and/or installation of roadway signage, guardrail adjustment and installation, improvements and/or replacement of Konohii Stream Bridge on Olohena Road including end treatments/safety rail transitions, utility relocations, and construction staging as needed
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map |
Phase:
Estimated Construcion Time:
2021/2022
Cost:
- Design: $826,000.00
- Construction: TBD
|
Po‘ipū Road Multimodal Improvements |
This Project will include roadway resurfacing and reconstruction, striping for vehicle and bicycle travel lanes, pedestrian sidewalks, crosswalks, parking, revised intersection traffic control including roundabouts, and drainage modifications in certain areas. There will be construction of sidewalks in Kōloa Town along Po‘ipū Road, construction of bicycle lanes on Po‘ipū Road, and improved transit serves along Po‘ipū Road.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map 1
Location Map 2
|
Phase:
Estimated Construcion Time:
2022/2023
Cost:
- Design: $2,102,420.00
- Construction: TBD
|
Safe Routes to School Improvements: Kalāheo Elementary School |
The Project plans to provide a safe route to Kalaheo Elementary School by reconstructing an ADA sidewalk on Puʻu Road from Papalina Road to Maka Road as well as constructing a new sidewalk along Hokua Road. It also aims to provide well-marked pedestrian crossings at key intersections, retain existing drainage patterns and on-street parking, and improve pedestrian access from remote drop-offs that reduce traffic congestion at the school.
Project Manager:
Aidan P. Smith
PH: (808) 241-4154
|
Conceptual Design |
Phase:
Cost:
- Design: $87,058.00
- Construction: TBD
|
Safe Routes to School Improvements: King Kaumuali‘i Elementary School |
This project plans to make pedestrian improvements and minor roadway widening including sidewalks, turn lanes, and crosswalks with rectangular rapid flashing beacons. There will also be adjustments of lot frontages, driveways, surface utilities, and drainage structures as necessary while remaining ADA compliant.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map |
Phase:
Cost:
- Design: $118,829.00
- Construction: $1,000,000.00
|
Safe Routes to School Improvements: Kōloa Elementary School |
This project plans to make pedestrian and bicycle improvements including sidewalks, approximately 5-feet shift of roadway within the right-of-way, lane restriping to provide shared-lanes and bike lanes, and crosswalks with rectangular rapid flashing beacons. There will also be adjustments of lot frontages, driveways, surface utilities, and drainage structures as necessary while remaining ADA compliant.
Project Manager:
Joel O. Bautista, P.E.
PH: (808) 241-4153
|
Location Map |
Phase:
Cost:
- Design: $117,410.00
- Construction: TBD
|
Waimea Levee Repair |
The Waimea levee was constructed in 1954 to protect the Waimea town from flooding from the Waimea River during large storms. The Waimea levee system includes outlets with flap gates to allow rainwater to drain from the town area into the Waimea River when the elevation of the river is lower than the elevation of the water in the drainage system behind the levee while also preventing the water from the river to flow into the Waimea Town drainage system. The levee outlets are also provided with sluice gates to allow the Waimea Town drainage system to be isolated manually from the Waimea River. Currently, the outlet for the Kealii Canal to the Waimea levee is inoperable, therefore this project aims to repair the sluice gates to help reduce flooding.
Project Manager:
Donald M. Fujimoto, P.E., M.B.A.
PH: (808) 241-4083
|
|
Phase:
Cost:
- Design: $300,000.00
- Construction: TBD
|