ACROW Bridge Yasutake
|
This Project plans to install 60 foot long pre-engineered Acrow Bridge system with approach ramps on either side at Kamalu Road, Wailua Homesteads, Kaua‘i, HI.
Project Manager:
Keith Perry
klperry@kauai.gov
PH: (808) 241-4950
|
2022 Press Release Closed Down - Yasutake
2022 Press Release Reopen - Yasutake
|
Phase:
|
Anahola Landing Bridge
|
This Project plans to replace the failed double barrel CMP culvert with concrete headwalls on both sides and other miscellaneous work.
Project Manager:
Joel O. Bautista, P.E.
|
2021 Press Release
|
Phase:
Cost:
- Design: $180,000
- Construction: TBD
|
Hanapēpē Bridge Repairs
|
This Project plans to repair spalled, delaminated, and cracked areas of concrete and corroded exposed reinforcing in the deck, girders, floor beams, abutments, pier walls, and parapets that contribute to the bridge's poor state. The existing asphalt concrete and base course on the deck will be removed, and a new concrete deck will be placed on top of the original deck along with an asphalt overlay. Additionally, the elevated walkway on the downstream side of the bridge, which was initially added in 1927, will be restored to operational condition by placing new, pre-formed concrete slabs for the walkway surface and sides.
Project Managers:
Aidan P. Smith, EIT
Nicholas Jefferies, EIT
|
Published Plan Set
Press Release of Bridge Closure
|
Phase:
Estimated Time:
July 22, 2024 - April 11, 2025
Cost:
- Design: $389,000
- Construction:$3,100,000
|
Hanapēpē Road Resurfacing
|
This project plans to reconstruct and rehabilitate Hanapēpē Road. This include resurfacing and reconstruction, installing and/or replacing centerline and survey monuments, signage, and striping for sharrow lanes, pedestrian lanes, crosswalks and parking.
Project Manager:
Joel O. Bautista, P.E.
|
Concept Design 2016
In-Progress 90% Plans
|
Phase:
Cost:
- Design: $480,000
- Construction: $3,900,000
|
Improvements to Maluhia Road (Route 520) & Kōloa Road (Route 530)
|
This Project will rehabilitate pavement on Kōloa Road, from Kaumuali‘i Highway to Po‘ipū Road, and Maluhia Road, from Kaumuali‘i Highway to Kōloa Road. This project also plans to extend the pavement shoulders by up to 6 feet in each direction, add a left turn auxiliary lane on Kōloa Road at Piko Road, add a left turn auxiliary lane on Kōloa Road at Lauoho Road, and add a left turn pocket on Maluhia Road to Ala Kinoiki. A roundabout will also be installed at the intersection of Kōloa Road and Ala Kalanikaumaka as well as guardrail repairs, drainage modifications, and other safety improvements.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map
|
Phase:
Cost:
- Design: $1,102,500
- Construction: $21,000,000
|
Kawaihau Road Improvements
|
This Project will make roadway improvements along Kawaihau Road between Ka‘apuni Road and Hau‘a‘ala Road. Potential roadway improvements consist of sidewalk improvements, curb and gutter improvements, left turn pockets, bike lanes, and other traffic calming improvements such as striping and signage, etc.
Project Manager:
Charlene Johnston, P.E.
|
Project Location Map
Walk Audit Map
Charrette PowerPoint Presentation
Charrette Review PowerPoint Presentation
|
Phase:
Cost:
- Design: $544,172
- Construction: TBD
|
Kawaihau-Hau‘a‘ala-Mailihuna Complete Streets Project
|
The Project aims to construct a peanut-shaped roundabout, sidewalks, paved shoulders, and various other roadway improvements to help improve the safety and operations of the 5-way intersection of these three roads and to people using multiple modes to travel efficiently and safely through Kawaihau Road, Hauʻaʻala Road, and Mailihuna Road located in Kapaʻa, Kauaʻi Island, Hawaiʻi. This area contains St. Catherine's School/Church, Kapaʻa High School, Kapaʻa Elementary School, Mahelona Hospital, and Gore Park.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map
Peanutabout Concept
|
Phase:
Cost:
- Design: $1,011,120
- Construction: $8,020,000.00
|
Kekaha Road and ‘Akialoa Road Improvements
|
The intention of the project is to rehabilitate & resurface the full lengths of Kekaha Road and ‘Akialoa Road (approximately 2.5 miles); implement corridor improvements such as sidewalks and bicycle enhancements on Kekaha Road, ‘Akialoa Road, and ‘Alae Road; and improve traffic flow at the intersection of Kekaha Road with ‘Alae Road and Kōke‘e Road.
Project Manager:
Charlene Johnston, P.E.
|
Project Location Map
Project Limits Map
Walk Audit Project Map
Charrette PowerPoint Presentation
Charrette Review PowerPoint Presentation
|
Phase:
Estimated Construction Time:
Cost:
- Pre-Design: $300,000
- Design: $500,000
- Construction: TBD
|
Kīlauea Point National Wildlife Refuge Access Improvements
|
Kīlauea Point National Wildlife Refuge (KPNWR) the United States Fish and Wildife Service (USFWS) along with the Federal Highway Administration (FHWA), Central Federal Lands Highway Division (CFLHD) are researching ways to improve the area by providing better access along Kolo Road and Kīlauea Road for pedestrians and bicyclists, as well as improvements to the overlook to improve safety. This project consists of installation of a sidewalk adjacent the existing roadway from the intersection of Kuhio Highway to the KPNWR Overlook. Work includes pavement mill and overlay on the existing roadway, with full depth pavement on aggregate base course for roadway widening segments, and reconstruction of the existing turnaround. Guardrail, sidewalk, curb, gutter, two mini-roundabouts, striping, and pedestrian crossings will be provided to establish a safe and accessible corridor for pedestrians and bicyclists.
Project Manager:
Aidan P. Smith, EIT
|
Location Map
100% Plans Set (Subject to change prior to construction)
|
Phase:
Cost:
- Design: $534,000
- Construction:
$15,000,000
|
Kīpū Bridge Repair
|
This Project will rehabilitate Kīpū Bridge to retain its original load capacity by preventing further loss of steel reinforcement and to install transitions between gaps of the bridge wall for safety.
Project Manager:
Aidan P. Smith, EIT
|
Location Map
Project Area
|
Phase:
Cost:
- Design: $208,854
- Construction:$1,000,000
|
Kōloa Bridge Repair
|
This Project will rehabilitate Kōloa Bridge by repairing the road surface, which will be repaved and restriped within the area of the bridge as well as immediately before and after the bridge. This rehabilitation also plans to fix spalls and delamination to prevent further loss of the exposed steel reinforcement, bring the bridge strength up to current standards by repairing and augmenting the beams, and add guardrails on the west and east sides of the bridge’s mauka-side wall.
Project Manager:
Aidan P. Smith, EIT
|
Project Area
|
Phase:
Cost:
- Design: $201,331
- Construction: $700,000
|
Niumalu Bridge
|
This Project will improve the safety for vehicles crossing the one-lane bridge at Pū‘ali Stream near Nāwiliwili Harbor as the current bridge is heavily spalled with a large amount of section loss in the exposed reinforcing steel. This improve will include rehabilitation of the existing, damaged concrete bridge deck that will match the original bridge in design, color, texture, and other visual qualities. New bridge ends will be constructed on dry land behind the existing ends and the new bridge deck will span over the existing ends. The existing ends will remain as-is.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map
|
Phase:
Cost:
- Design: $374,291
- Construction: TBD
|
Olohena Road (RTE 581) Resurfacing
|
This Project, located in the Kawaihau District, will include pavement restriping, roadway surfacing, shoulder widening, construction of sidewalks, striping of pedestrian crossings, improvements to accessible routes, reconfiguration and/or addition/deletion of travel lanes, turn lanes, bike lanes, and parking areas, replacement or upgrades to bus stops, vegetation removal, removal of trees that endanger life or property, storm drainage improvements, replacement and/or installation of roadway signage, guardrail adjustment and installation, improvements and/or replacement of Konohii Stream Bridge on Olohena Road including end treatments/safety rail transitions, utility relocations, and construction staging as needed.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map
|
Phase:
Estimated Construction Time:
Cost:
- Design: $826,000
- Construction: $14,870,000
|
Po‘ipū Road Safety and Mobility
|
This Project will include roadway resurfacing and reconstruction, striping for vehicle and bicycle travel lanes, pedestrian sidewalks, crosswalks, parking, revised intersection traffic control including roundabouts, and drainage modifications in certain areas. There will be construction of sidewalks in Kōloa Town along Po‘ipū Road, construction of bicycle lanes on Po‘ipū Road, and improved transit serves along Po‘ipū Road. The federal funding obligation will occur in approximately August 2024, with the construction of project starting in the spring of 2025.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map 1
Location Map 2
100% Plans Set (Subject to change prior to construction)
|
Phase:
Estimated Construction Start Time:
Cost:
- Design: $2,100,000
- Construction:
$53,000,000
|
Puhi Road Rehabilitation Phase II
|
This Project will improve the portion of Puhi Road between Kaneka Street and Haleukana Street. The proposed improvements for the project include reconstruction of Puhi Road’s weakened pavements using asphalt concrete and/or Portland cement concrete, widening the roadway to accommodate new bike lanes and areas of parallel parking, a new sidewalk for the west side of Puhi Road between Kaneka and Hanalima Streets, and a new shared-use path long the entire east side of the road.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map
|
Phase:
Cost:
- Design: $309,380
- Construction: $7,380,000
|
Safe Routes to School Improvements: Kalāheo Elementary School
|
The Project plans to provide a safe route to Kalaheo Elementary School by reconstructing an ADA sidewalk on Puʻu Road from Papalina Road to Maka Road as well as constructing a new sidewalk along Hokua Road. It also aims to provide well-marked pedestrian crossings at key intersections, retain existing drainage patterns and on-street parking, and improve pedestrian access from remote drop-offs that reduce traffic congestion at the school.
Project Manager:
Aidan P. Smith, EIT
|
Conceptual Design
|
Phase:
Cost:
- Design: $87,058
- Construction: TBD
|
Safe Routes to School Improvements: King Kaumuali‘i Elementary School
|
This Project plans to make pedestrian improvements and minor roadway widening including sidewalks, turn lanes, and crosswalks with rectangular rapid flashing beacons. There will also be adjustments of lot frontages, driveways, surface utilities, and drainage structures as necessary while remaining ADA compliant.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map
|
Phase:
Cost:
- Design: $118,829
- Construction: $1,000,000
|
Safe Routes to School Improvements: Kōloa Elementary School
|
This Project plans to make pedestrian and bicycle improvements including sidewalks, approximately 5-feet shift of roadway within the right-of-way, lane restriping to provide shared-lanes and bike lanes, and crosswalks with rectangular rapid flashing beacons. There will also be adjustments of lot frontages, driveways, surface utilities, and drainage structures as necessary while remaining ADA compliant.
Project Manager:
Joel O. Bautista, P.E.
|
Location Map
|
Phase:
Cost:
- Design: $117,410
- Construction: $1,304,000
|
Waimea Levee Repair
|
The Waimea levee was constructed in 1954 to protect the Waimea town from flooding from the Waimea River during large storms. The Waimea levee system includes outlets with flap gates to allow rainwater to drain from the town area into the Waimea River when the elevation of the river is lower than the elevation of the water in the drainage system behind the levee while also preventing the water from the river to flow into the Waimea Town drainage system. The levee outlets are also provided with sluice gates to allow the Waimea Town drainage system to be isolated manually from the Waimea River. Currently, the outlet for the Kealii Canal to the Waimea levee is inoperable, therefore this project aims to repair the sluice gates to help reduce flooding.
Project Manager:
Donald M. Fujimoto, P.E., M.B.A.
|
|
Phase:
Cost:
- Design: $300,000
- Construction: $1,900,000
|